De-Shuttering Period of Different RCC Members

The period for columns, walls, and vertical formworks – is 16-24 hrs.

Period for Soffit formwork to slabs – 3 days (props to be refixed after removal)

The period for Soffit to beams props – is 7 days (props to be refixed after removal)

Beams spanning up to 4.5m – 7 days

Beams spanning over 4.5m – 14 days

Arches spanning up to 6m – 14 days

Arches spanning over 6m – 21 days