S.No |
Structural Member |
OPC (Ordinary Portland Cement) |
Rapid Hardening Cement |
1 | Beam sides, walls & Columns | 2-3 Days | 2 Days |
2 | Slab (Vertical Supports remains intact) | 4 Days | 3 Days |
3 | Slab (Complete Formwork removal) | 10 Days | 5 Days |
4 | Beams (Removal of Sheeting, Props remains intact) | 8 Days | 5 Days |
5 | Beams & Arches (Complete formwork removal) (up to 6m span) | 14 Days | 5-8 Days |
6 | Beams & Arches (Complete formwork removal) (more than 6m span) | 21 Days | 8-10 Days |