Labour Requirement for 1cum of RCC

Labours required are presented in terms of days required by particular labour to complete its work for the given quantity of concrete. Following are the various labours required:

Mason:

As per Standard Schedule of Rates and Analysis of Rates, One mason is required for 0.37 days.

Labours:

One Unskilled labours required for 3.5 days.

Water carrier:

One water carrier required for 1.39 days.

Bar Bender:

Bar bender requirement depends on weight of reinforcement. Let’s consider one bar bender required for 100 kg of steel as for 1 day.

Mixer Operator:

One mixer operator required for 0.0714 days.

Vibrator Operator:

One vibrator operator required for 0.0714 days.

 