Labours required are presented in terms of days required by particular labour to complete its work for the given quantity of concrete. Following are the various labours required:
Mason:
As per Standard Schedule of Rates and Analysis of Rates, One mason is required for 0.37 days.
Labours:
One Unskilled labours required for 3.5 days.
Water carrier:
One water carrier required for 1.39 days.
Bar Bender:
Bar bender requirement depends on weight of reinforcement. Let’s consider one bar bender required for 100 kg of steel as for 1 day.
Mixer Operator:
One mixer operator required for 0.0714 days.
Vibrator Operator:
One vibrator operator required for 0.0714 days.