Concrete Staining Procedure

The concrete staining process is moderately difficult, affordable, and may take up to two days. The following are the steps involved in concrete straining:

Preparation of Concrete Surface

  • Irrespective of the age of the concrete, it is important to prepare the concrete surface carefully.
  • The concrete surface is cleaned thoroughly for dirt, residues, and any grime by using mechanical grinding or concrete cleaning solutions and degreasers.
  • Any existing coating/staining on the concrete surface shall be removed before staining.
  • If any concrete cracks are found, they shall be sealed with concrete crack sealants.
  • Uneven patches are buffed using a floor scrubber.